Diagnostic Test
WARNING: This page is about a different variant/trim than selected.
- CHECK FOR AN ACTIVE DTC
- Turn the ignition on.
- With the scan tool, erase DTCs in the PCM-1.
- Perform several ignition key cycles, pausing for at least ten seconds between each cycle.
- Turn the ignition on.
- With the scan tool, read DTCs and record on the repair order.
Did this DTC return?
Yes
- Go To 2
No
- Perform the INTERMITTENT DTC diagnostic procedure. Refer to INTERMITTENT CONDITION .
- CHECK THE BATTERY SUPPLY TO THE ASD RELAY CONTROL CIRCUIT
- Turn the ignition off.
- Remove the ASD Relay from the PDC.
- Turn the ignition on, engine not running.
- Using a 12-volt test light connected to ground voltage, probe the Battery supply for the (K51) ASD Relay Control circuit in the ASD Relay connector.
Does the test light illuminate brightly?
Yes
- Go To 3
No
- Repair the Battery supply for an open or high resistance. If the fuse is found to be open, repair the ASD Relay Output circuit for a short to ground.
- Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
- CHECK THE ASD RELAY FOR PROPER OPERATION
- Turn the ignition off.
- Install a known good relay in place of the ASD Relay.
- Turn the ignition on.
- With the scan tool, erase DTCs in the PCM-1.
- Perform several ignition key cycles, pausing for at least ten seconds between each cycle.
- Turn the ignition on.
- With the scan tool, read DTCs.
Did this DTC return?
Yes
- Go To 4
No
- Repair complete.
- Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
- CHECK THE (K51) ASD RELAY CONTROL CIRCUIT FOR A SHORT TO ANOTHER VOLTAGE SUPPLY CIRCUIT
- Turn the ignition off.
- Remove the ASD Relay from the Power Distribution Center (PDC).
- Disconnect the PCM-1 C1 harness connector.
- Check for continuity between the (K51) ASD Relay Control circuit and all other 5 volt and 12 volt supply circuits at the PCM-1 C1 harness connector.
Is there continuity between the (K51) ASD Relay Control circuit and any other 5 volt and 12 volt supply circuits?
Yes
- Repair the (K51) ASD Relay Control circuit for a short to the circuit that showed continuity.
- Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
No
- Go To 5
- CHECK THE (K51) ASD RELAY CONTROL CIRCUIT FOR A SHORT TO GROUND
- Check for continuity between ground and the (K51) ASD Relay Control circuit at the PCM-1 C1 harness connector.
Is there continuity between ground and the (K51) ASD Relay Control circuit?
Yes
- Repair the (K51) ASD Relay Control circuit for a short to ground.
- Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
No
- Go To 6
- Check for continuity between ground and the (K51) ASD Relay Control circuit at the PCM-1 C1 harness connector.
- CHECK THE (K51) ASD RELAY CONTROL CIRCUIT FOR AN OPEN/HIGH RESISTANCE
- Measure the resistance of the (K51) ASD Relay Control circuit between the ASD Relay connector and the PCM-1 C1 harness connector.
Is the resistance below 3.0 Ohms?
Yes
- Go To 7
No
- Repair the ASD Relay Control circuit for an open or high resistance.
- Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
- Measure the resistance of the (K51) ASD Relay Control circuit between the ASD Relay connector and the PCM-1 C1 harness connector.
- CHECK RELATED HARNESS CONNECTIONS
- Disconnect all PCM-1 harness connectors.
- Disconnect all related in-line harness connections (if equipped).
- Disconnect the related component harness connectors.
- Inspect harness connectors, component connectors, and all male and female terminals for the following conditions:
- Proper connector installation.
- Damaged connector locks.
- Corrosion.
- Other signs of water intrusion.
- Weather seal damage (if equipped).
- Bent terminals.
- Overheating due to a poor connection (terminal may be discolored due to excessive current draw).
- Terminals that have been pushed back into the connector cavity.
- Check for spread terminals and verify proper terminal tension.
Repair any conditions that are found.
- Connect all PCM-1 harness connectors. Be certain that all harness connectors are fully seated and the connector locks are fully engaged.
- Connect all in-line harness connectors (if equipped). Be certain that all connectors are fully seated and the connector locks are fully engaged.
- Connect all related component harness connectors. Be certain that all connectors are fully seated and the connector locks are fully engaged.
- With the scan tool, erase DTCs.
- Test drive or operate the vehicle in accordance with the when monitored and set conditions.
- With the scan tool, read DTCs.
Did the DTC return?
Yes
- Replace and program the Powertrain Control Module 1 (PCM-1) in accordance with the Service Information. Refer to MODULE, POWERTRAIN CONTROL (PCM), REMOVAL AND INSTALLATION .
- Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
No
- The wiring or poor connection problem has been repaired.
- Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .