  1. CHECK FOR AN ACTIVE DTC 
    1. With the scan tool, read Powertrain Control Module 1 (PCM-1) DTCs and Freeze Frame Data and record on the repair order.
    2. Using the recorded Freeze Frame Data and the When Monitored and Set Conditions above, operate the vehicle in the conditions that set the DTC.
    3. With the scan tool, read PCM-1 DTCs.

      Is the DTC active or pending?

      Yes 

      • Go To  2

      No 

  2. CHECK THE (K13) INJECTOR 3 CONTROL CIRCUIT FOR AN OPEN/HIGH RESISTANCE 
    1. Turn the ignition off.
    2. Disconnect the PCM-1 C2 harness connector.
    3. Disconnect the Fuel Injector 3 harness connector.
    4. Measure the resistance of the (K13) Injector 3 Control circuit between the Fuel Injector 3 harness connector and the PCM-1 C2 harness connector.

      Is the resistance below 3.0 Ohms?

      Yes 

      • Go To  3

      No 

      • Repair the (K13) Injector 3 Control circuit for an open or high resistance.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
  3. CHECK THE (K613) INJECTOR 3 LOW SIDE CONTROL CIRCUIT FOR AN OPEN/HIGH RESISTANCE 
    1. Measure the resistance of the (K613) Injector 3 Low Side Control circuit between the Fuel Injector 3 harness connector and the PCM-1 C2 harness connector.

      Is the resistance below 3.0 Ohms?

      Yes 

      • Go To  4

      No 

      • Repair the (K613) Injector 3 Low Side Control circuit for an open or high resistance.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
  4. CHECK THE FUEL INJECTOR 3 RESISTANCE 
    1. Measure the resistance of Fuel Injector 3.
      NOTE:

      Compare the resistance to other known good injectors on the vehicle.

      Is the resistance of the Fuel Injector 1 within 10% of the other known good injectors?

      Yes 

      • Go To  5

      No 

  5. CHECK RELATED PCM AND COMPONENT CONNECTIONS 
    1. Perform any Service Bulletins that apply.
    2. Disconnect all PCM-1 harness connectors.
    3. Disconnect all related in-line harness connections (if equipped).
    4. Disconnect the related component harness connectors.
    5. Inspect harness connectors, component connectors, and all male and female terminals for the following conditions:
      • Proper connector installation.
      • Damaged connector locks.
      • Corrosion.
      • Other signs of water intrusion.
      • Weather seal damage (if equipped).
      • Bent terminals.
      • Overheating due to a poor connection (terminal may be discolored due to excessive current draw).
      • Terminals that have been pushed back into the connector cavity.
      • Check for spread terminals and verify proper terminal tension.

      Repair any conditions that are found.

    6. Reconnect all PCM-1 harness connectors. Be certain that all harness connectors are fully seated and the connector locks are fully engaged.
    7. Reconnect all in-line harness connectors (if equipped). Be certain that all connectors are fully seated and the connector locks are fully engaged.
    8. Reconnect all related component harness connectors. Be certain that all connectors are fully seated and the connector locks are fully engaged.
    9. With the scan tool, erase DTCs.
    10. Test drive or operate the vehicle in accordance with the when monitored and set conditions.
    11. With the scan tool, read DTCs.

      Did the DTC return?

      Yes 

      No