Diagnostic Test

  1. CHECK FOR AN ACTIVE DTC 
    1. With the scan tool, read Powertrain Control Module (PCM) DTCs and Freeze Frame Data and record on the repair order.
    2. Using the recorded Freeze Frame Data and the When Monitored and Set Conditions above, operate the vehicle in the conditions that set the DTC.
    3. With the scan tool, read and record DTCs and Freeze Frame Data on the repair order.

      Is the DTC active or pending?

      Yes 

      • Go To  2

      No 

  2. CHECK THE (K187) COOLANT BYPASS VALVE CONTROL CIRCUIT FOR A SHORT TO VOLTAGE 
    1. Turn the ignition off.
    2. Disconnect the Coolant Bypass Valve harness connector.
    3. Disconnect the PCM C1 harness connector.
    4. Check for continuity between the (K187) Coolant Bypass Valve Control circuit and all other circuits at the PCM C1 harness connector.

      Is there continuity between the (K187) Coolant Bypass Valve Control circuit and any other circuit?

      Yes 

      • Repair the (K187) Coolant Bypass Valve Control circuit for a short to the circuit that showed continuity.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .

      No 

      • Go To  3
  3. CHECK THE (K187) COOLANT BYPASS VALVE CONTROL CIRCUIT FOR AN OPEN/HIGH RESISTANCE 
    1. Measure the resistance of the (K187) Coolant Bypass Valve Control circuit between the Coolant Valve Bypass Valve harness connector and the PCM C1 harness connector.

      Is the resistance below 3.0 Ohms?

      Yes 

      • Go To  4

      No 

      • Repair the (K187) Coolant Bypass Valve Control circuit for an open or high resistance.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
  4. CHECK THE (Z101) GROUND CIRCUIT FOR AN OPEN/HIGH RESISTANCE 
    1. Measure the resistance between ground and the (Z101) Ground circuit at the Coolant Bypass Valve harness connector.

      Is the resistance below 3.0 Ohms?

      Yes 

      • Go To  5

      No 

      • Repair the (Z101) Ground circuit for an open or high resistance.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .
  5. CHECK THE ENGINE COOLANT BYPASS VALVE FOR PROPER OPERATION 
    1. Reconnect the PCM C1 harness connector.
    2. Connect a jumper between the (K187) Coolant Bypass Valve Control circuit and the (Z101) Ground circuit at the Coolant Bypass Valve harness connector.
    3. Turn the ignition on.

      Is the P022B-CHARGE AIR COOLER BYPASS VALVE CONTROL CIRCUIT LOW DTC active or pending with the jumper in place?

      Yes 

      • Replace the Cooler Bypass Valve in accordance with the Service Information.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .

      No 

      • Go To  6
  6. CHECK RELATED HARNESS CONNECTIONS 
    1. Disconnect all PCM harness connectors.
    2. Disconnect all related in-line harness connections (if equipped).
    3. Disconnect the related component harness connectors.
    4. Inspect harness connectors, component connectors, and all male and female terminals for the following conditions:
      • Proper connector installation.
      • Damaged connector locks.
      • Corrosion.
      • Other signs of water intrusion.
      • Weather seal damage (if equipped).
      • Bent terminals.
      • Overheating due to a poor connection (terminal may be discolored due to excessive current draw).
      • Terminals that have been pushed back into the connector cavity.
      • Check for spread terminals and verify proper terminal tension.

      Repair any conditions that are found.

    5. Connect all PCM harness connectors. Be certain that all harness connectors are fully seated and the connector locks are fully engaged.
    6. Connect all in-line harness connectors (if equipped). Be certain that all connectors are fully seated and the connector locks are fully engaged.
    7. Connect all related component harness connectors. Be certain that all connectors are fully seated and the connector locks are fully engaged.
    8. With the scan tool, erase DTCs.
    9. Test drive or operate the vehicle in accordance with the when monitored and set conditions.
    10. With the scan tool, read DTCs.

      Did the DTC return?

      Yes 

      No 

      • The wiring or poor connection problem has been repaired.
      • Perform the POWERTRAIN VERIFICATION TEST. Refer to POWERTRAIN VERIFICATION TEST .